IC-IR Consultant Contract-Phase 3

This project provides consultant support for approximately 25 Missouri Department of Transportation (MoDOT) projects for the 2019 construction season. The consultant has developed and lead contractor Intelligent Compaction (IC) and Infrared (IR) training for MoDOT projects in previous years. This current research project will provide training, data and field support for each of the IC-IR MoDOT Asphalt Projects constructed in 2019.

  • Supplemental Notes:
    • Quarterly Progress: In October the research team provided field support for the Route 130 project in Putnam County that was paved by Norris Asphalt. The research staff also provided remote support for an I-35 project in Harrison County by Herzog from October to November 2018, a Route 61 project in Cape Girardeau County by Chester Bross from September to November 2018, and a Route 54 project in Callaway County by Capital Paving from October to November 2018.

Language

  • English

Project

  • Status: Active
  • Funding: $199852
  • Contract Numbers:

    TR201902

  • Sponsor Organizations:

    Missouri Department of Transportation

    1617 Missouri Boulevard
    P.O. Box 270
    Jefferson City, MO  United States  65102
  • Project Managers:

    Harper, Jennifer

  • Performing Organizations:

    Transtec Group

    6111 Balcones Drive
    Austin, TX  United States  78731
  • Principal Investigators:

    Chang, George

  • Start Date: 20180701
  • Expected Completion Date: 20200131
  • Actual Completion Date: 0

Subject/Index Terms

Filing Info

  • Accession Number: 01692142
  • Record Type: Research project
  • Source Agency: Missouri Department of Transportation
  • Contract Numbers: TR201902
  • Files: RiP, STATEDOT
  • Created Date: Feb 1 2019 11:50AM