Dynamic Subcomponent Testing and Finite Element Simulation of Guardrail Systems with Alternative Post Installation Methodologies

The objective of this project is to develop alternatives to the guardrail post installation methodology outlined in the American Association of State Highway and Transportation (AASHTO) Roadside Design Gide.

    Language

    • English

    Project

    • Status: Active
    • Funding: $491547
    • Contract Numbers:

      GDOT RP 15-08

    • Sponsor Organizations:

      Georgia Department of Transportation

      One Georgia Center
      600 West Peachtree Street, NW
      Atlanta, GA  United States  30308
    • Project Managers:

      Sims, Gretel

    • Performing Organizations:

      Georgia Institute of Technology, Atlanta

      School of Civil and Environmental Engineering
      790 Atlantic Drive
      Atlanta, GA  United States  30332-0355
    • Principal Investigators:

      Scott, David

    • Start Date: 20160122
    • Expected Completion Date: 20171122
    • Actual Completion Date: 0

    Subject/Index Terms

    Filing Info

    • Accession Number: 01590803
    • Record Type: Research project
    • Source Agency: Georgia Department of Transportation
    • Contract Numbers: GDOT RP 15-08
    • Files: RiP, STATEDOT
    • Created Date: Feb 23 2016 9:09AM