Evaluation of Warm Mix Asphalt (WMA) Pavement

This experimental features project originally consisted of three different WMA projects throughout the state. The project was revised to include only the I 15 project. The Monida-Lima (SB), I 15 project consisted of placing three types of warm mix asphalts with different technologies (Evotherm, Sasobit, and foaming) and a hot mix asphalt control section. Each section of the different technologies is approximately a quarter of the project length. The beginning and ending point of each section and the product used will be clearly defined. The objective of this research project is to determine the effectiveness of Warm Mix Asphalt (WMA) using three WMA additives and technologies compared to MDT's standard Hot Mix Asphalt (HMA) surfacing.

Language

  • English

Project

  • Status: Active
  • Contract Numbers:

    MT 10-02

    IM 15-1(109)0

  • Sponsor Organizations:

    Federal Highway Administration

    Office of Natural Environment, 1200 New Jersey Avenue, SE
    Washington, DC  United States  20590

    Montana Department of Transportation

    2701 Prospect Avenue
    P.O. Box 201001
    Helena, MT  United States  59620-1001
  • Project Managers:

    Christensen, Kris

  • Performing Organizations:

    Montana Department of Transportation

    2701 Prospect Avenue
    P.O. Box 201001
    Helena, MT  United States  59620-1001
  • Start Date: 20131013
  • Expected Completion Date: 0
  • Actual Completion Date: 0
  • Source Data: RiP Project 35632

Subject/Index Terms

Filing Info

  • Accession Number: 01497519
  • Record Type: Research project
  • Source Agency: Montana Department of Transportation
  • Contract Numbers: MT 10-02, IM 15-1(109)0
  • Files: RiP, STATEDOT
  • Created Date: Nov 6 2013 1:00AM