Research for the AASHTO Standing Committee on the Environment. Task 28. Reevaluations of NEPA Documents

<font size="3">At times, delays in project development process force the project to wait years before proceeding to construction. All the while, the environmental studies that were conducted early have a shelf life and may need a refreshing prior to the project moving forward. Not only do the National Environmental Protection Agency (NEPA) documents have a shelf life, but so do the specific environmental studies to go into it. Every state conducts reevaluations of their NEPA documents and specific studies, but recently several states have had problems with the detail necessary, the processing of these reevaluations and knowing exactly what studies need refreshed, to what degree and how often. This task will develop a guide for NEPA professionals on when reevaluations are needed, to what degree of detail and how often they require to be produced.</font>

Language

  • English

Project

  • Status: Completed
  • Funding: $55000.00
  • Contract Numbers:

    Project 25-25, Task

  • Sponsor Organizations:

    Federal Highway Administration

    1200 New Jersey Avenue, SE
    Washington, DC  United States  20590

    American Association of State Highway and Transportation Officials (AASHTO)

    444 North Capitol Street, NW
    Washington, DC  United States  20001

    National Cooperative Highway Research Program

    Transportation Research Board
    500 Fifth Street, NW
    Washington, DC  United States  20001
  • Project Managers:

    Hedges, Christopher

  • Performing Organizations:

    ICF Consulting, Incorporated

    101 Lucas Valley Road
    San Rafael, CA  United States  94903-1791
  • Principal Investigators:

    Hansel, John

  • Start Date: 20070222
  • Expected Completion Date: 0
  • Actual Completion Date: 20080401
  • Source Data: RiP Project 16337

Subject/Index Terms

Filing Info

  • Accession Number: 01464634
  • Record Type: Research project
  • Source Agency: National Cooperative Highway Research Program
  • Contract Numbers: Project 25-25, Task
  • Files: TRB, RiP, USDOT