Implementation of Semi-integral Bridges in Texas

The research team will validate predicted semi-integral bridge performance against actual semi-integral bridge performance; particularly regarding backfill placement requirements. In particular, the geotextile-confined backfill will be monitored to assess its impact on (1) the lateral earth pressures induced due to cycles of temperature-induced backfill movements and (2) the settlements of the backfill material. The new approach, developed in research project 0-6936, is expected to reduce lateral earth pressures and decrease settlements. This validation of field performance will facilitate the development of a standard detail and commentary for the Bridge Design Manual as well as the compilation of additional design and construction guidelines. The research team will also monitor the semi-integral bridge at China Creek, in the Wichita Falls District using the wireless field monitoring system installed during research project 0-6936.

Language

  • English

Project

  • Status: Active
  • Funding: $780,032
  • Contract Numbers:

    5-6936-01

  • Sponsor Organizations:

    Texas Department of Transportation

    125 E. 11th Street
    Austin, TX  United States  78701-2483
  • Managing Organizations:

    Texas Department of Transportation

    125 E. 11th Street
    Austin, TX  United States  78701-2483
  • Project Managers:

    Adediwura, Jade

  • Performing Organizations:

    Center for Transportation Research

    3925 W. Braker Lane
    Austin, TX  United States  78759
  • Principal Investigators:

    Zomberg, J

  • Start Date: 20240214
  • Expected Completion Date: 20270831
  • Actual Completion Date: 0

Subject/Index Terms

Filing Info

  • Accession Number: 01909000
  • Record Type: Research project
  • Source Agency: Texas Department of Transportation
  • Contract Numbers: 5-6936-01
  • Files: RIP, STATEDOT
  • Created Date: Feb 20 2024 3:49PM